Sprint Plan(Tentative)- Miami Benchmark -Q4
Team mission
Project - Miami Benchmark
Tentative Road Map till Jan, 2025 (First 4 Sprints)
Sprint Breakdown:
The roadmap consists of four sprints, each lasting 3 weeks (21 days), divided into 2 weeks of development and 1 week of testing and bug fixing.
Here's the detailed breakdown:
MB Sprint 1: ( *Need to update dates in JIRA Board and get permissions to create roadMap time line in JIRA)
A)Sprint Cycle Starts: Started
1.MB Sprint-1 Grooming - Done (Stacy,Jake,BAs and Dev Team)
2.MB Sprint-1 Planning - Done (Stacy,Jake,BAs and Dev Team)
B)Development Cycle: (Daily Scrum calls - Ongoing)
Sprint Start: October 1, 2024
Development End: October 15, 2024
Testing Start: October 15, 2024
Testing End: October 22, 2024
Sprint End: October 22, 2024
C) MB Sprint -1 Review - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Date - October 21-22, 2024 ( **We can have either 1 hr each day or 2-3 Hrs same day based on every one’s availability)
D) MB Sprint -1 Retrospective Meeting - (BAs, Dev team Only)
Date - Friday October 25 ,2024
—————————————————————————————————————————————————
MB Sprint 2:
A)Sprint Cycle Starts: Tuesday, October 08, 2024 (**for BA and PMO team to start grooming tickets for next sprint)
1.MB Sprint-2 Grooming - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Session 1 - Tuesday, October 08, 2024
Session 2 - Tuesday, October 15, 2024
2.MB Sprint-2 Planning - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Date - October 22-23, 2024 ( to keep 1 day before next sprint start for any followup question, ticket update etc)
B)Development Cycle: (Daily Scrum calls - Ongoing)
Sprint Start: October 24, 2024
Development End: November 7, 2024
Testing Start: November 8, 2024
Testing End: November 15, 2024
Sprint End: November 15, 2024
C) MB Sprint-2 Review - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Date - Thursday , November 14, 2024
D) MB Sprint-2 Retrospective Meeting - (BAs, Dev team Only)
Date - Friday , November 15, 2024
—————————————————————————————————————————————————
MB Sprint 3:
A)Sprint Cycle Starts: Tuesday November 05, 2024 ( **For BAs and PMO to start ticket grooming for MB Sprint -3)
1.MB Sprint-3 Grooming - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Session 1 - Tuesday November 05, 2024
Session 2 - Tuesday November 12, 2024
2.MB Sprint-3 Planning - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Date - Monday, November 18 -19 , 2024
B)Development Cycle: (Daily Scrum calls - Ongoing)
Sprint Start: November 20, 2024
Development End: December 4, 2024
Testing Start: December 4, 2024
Testing End: December 11, 2024
Sprint End: December 11, 2024
C) MB Sprint-3 Review - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Date - December 10-11, 2024
D) MB Sprint-3 Retrospective Meeting - (BAs, Dev team Only)
Date - Friday , December 13, 2024.
—————————————————————————————————————————————————
MB Sprint 4: (** Dates might change in case of additional holidays and code freeze durring festive session)
A)Sprint Cycle Starts:Monday ,December 09,2024 (**For BAs and PMO to start ticket grooming for MB Sprint -4)
1.MB Sprint-4 Grooming - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Session 1 - Monday ,December 09,2024
Session 2 - Thursday ,December 12,2024
2.MB Sprint-4 Planning - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Date - Monday December 16- 17, 2024
B)Development Cycle: (Daily Scrum calls - Ongoing)
Sprint Start: December 18, 2024
Development End: December 27, 2024
Testing Start: December 30, 2024
Testing End: January 7, 2025
Sprint End: January 7, 2025
C) MB Sprint-4 Review -(Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)
Date - January, 06, 2025
D) MB Sprint-4 Retrospective Meeting - (BAs, Dev team Only)
Date - January, 07,2025
++ Next Sprint Planning based on holiday/ PTO durring Holiday Session….
—————————————————————————————————————————————————
Holiday Considerations:
The roadmap takes into account both US and Indian holidays, adjusting sprint dates accordingly.
The following holidays are incorporated:
October 2, 2024: Gandhi Jayanti (India)
October 24, 2024: Diwali (India)
November 11, 2024: Veterans Day (US)
November 28, 2024: Thanksgiving (US)
December 25, 2024: Christmas (US and India)
NOTE: Additional Holidays and vacations Durring Christmas and New Year is not counted in yet, I will update MB Sprint -4 and MB Sprint 5 Plans accordingly after confirmations on dates with Dev team and PMO.
Cool-off Periods/Buffers:
A cool-off period of 3 days has been included after every two sprint cycles.
This is reflected in the gap between Sprint 2 and Sprint 3, which allows the team to recharge and conduct any necessary planning or retrospective activities.
NOTE : **We Need to incorporate teams PTOs as soon as available to manage bandwidth for each sprint durring Sprint planning sessions.
Project information
Roadmap overview
Detailed quarterly roadmap
Q1
Feature | Initiative | Dates | Priority | Effort | Status | Notes |
---|---|---|---|---|---|---|
High /Medium /Low | High /Medium /Low | In progress /not started /Shipped
| ||||
|
|
|
|
|
|
|
Q2
Feature | Initiative | Dates | Priority | Effort | Status | Notes |
---|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Q3
Feature | Initiative | Dates | Priority | Effort | Status | Notes |
---|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Q4
Feature | Initiative | Dates | Priority | Effort | Status | Notes |
---|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|