Sprint Plan(Tentative)- Miami Benchmark -Q4


Team mission

Project - Miami Benchmark

Tentative Road Map till Jan, 2025 (First 4 Sprints)

Sprint Breakdown:

The roadmap consists of four sprints, each lasting 3 weeks (21 days), divided into 2 weeks of development and 1 week of testing and bug fixing.

Here's the detailed breakdown:


MB Sprint 1: ( *Need to update dates in JIRA Board and get permissions to create roadMap time line in JIRA)

A)Sprint Cycle Starts: Started 

  1.MB Sprint-1 Grooming - Done (Stacey,Steve,Beverly,BAs and Dev Team)

2.MB Sprint-1 Planning -  Done  (Stacey,Steve,Beverly,BAs and Dev Team)

B)Development Cycle: (Daily Scrum calls - Ongoing)

  • Sprint Start: October 1, 2024

  • Development End: October 15, 2024

  • Testing Start: October 15, 2024

  • Testing End: October 22, 2024

  • Sprint End: October 22, 2024

C) MB Sprint -1 Review -  (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Date - October 21-22, 2024 ( **We can have either 1 hr each day or 2-3 Hrs same day based on every one’s availability)

D) MB Sprint -1 Retrospective Meeting - (BAs, Dev team Only)

    Date - Friday October 25 ,2024 

—————————————————————————————————————————————————

MB Sprint 2:

A)Sprint Cycle Starts: Tuesday, October 08, 2024 (**for BA and PMO team to start grooming tickets for next sprint)

  1.MB Sprint-2 Grooming - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Session 1 -  Tuesday, October 08, 2024

   Session 2 -  Tuesday, October 15, 2024  

2.MB Sprint-2 Planning - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Date -  October 22-23, 2024 ( to keep 1 day before next sprint start for any followup question, ticket update etc)

B)Development Cycle:  (Daily Scrum calls - Ongoing)

  • Sprint Start: October 24, 2024

  • Development End: November 7, 2024

  • Testing Start: November 8, 2024

  • Testing End: November 15, 2024

  • Sprint End: November 15, 2024

C) MB Sprint-2 Review -  (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Date - Thursday , November 14, 2024

D) MB Sprint-2 Retrospective Meeting - (BAs, Dev team Only)

    Date - Friday , November 15, 2024


—————————————————————————————————————————————————

MB Sprint 3:

A)Sprint Cycle Starts: Tuesday November 05, 2024 ( **For BAs and PMO to start ticket grooming for MB Sprint -3)

  1.MB Sprint-3 Grooming - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Session 1 - Tuesday November 05, 2024

   Session 2 - Tuesday November 12, 2024 


  2.MB Sprint-3 Planning - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

  Date - Monday, November 18 -19 , 2024

B)Development Cycle:  (Daily Scrum calls - Ongoing)

  • Sprint Start: November 20, 2024

  • Development End: December 4, 2024

  • Testing Start: December 4, 2024

  • Testing End: December 11, 2024

  • Sprint End: December 11, 2024

C) MB Sprint-3 Review - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Date - December 10-11, 2024

D) MB Sprint-3 Retrospective Meeting - (BAs, Dev team Only)

    Date - Friday , December 13, 2024.


—————————————————————————————————————————————————

MB Sprint 4: (** Dates might change in case of additional holidays and code freeze durring festive session)

A)Sprint Cycle Starts:Monday ,December 09,2024 (**For BAs and PMO to start ticket grooming for MB Sprint -4)

  1.MB Sprint-4 Grooming - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Session 1 -  Monday ,December 09,2024 

   Session 2 -  Thursday ,December 12,2024 

  2.MB Sprint-4 Planning - (Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

  Date - Monday December 16- 17, 2024

B)Development Cycle:  (Daily Scrum calls - Ongoing)

  • Sprint Start: December 18, 2024

  • Development End: December 27, 2024

  • Testing Start: December 30, 2024

  • Testing End: January 7, 2025

  • Sprint End: January 7, 2025

C) MB Sprint-4 Review -(Attendees Required - Kelli, Beverly, Steve, Stacy, Todd, BAs and Dev Team)

   Date - January, 06, 2025

D) MB Sprint-4 Retrospective Meeting - (BAs, Dev team Only)

    Date - January, 07,2025

++ Next Sprint Planning based on holiday/ PTO durring Holiday Session….

—————————————————————————————————————————————————

Holiday Considerations:

The roadmap takes into account both US and Indian holidays, adjusting sprint dates accordingly. 

The following holidays are incorporated:

  • October 2, 2024: Gandhi Jayanti (India)

  • October 24, 2024: Diwali (India)

  • November 11, 2024: Veterans Day (US)

  • November 28, 2024: Thanksgiving (US)

  • December 25, 2024: Christmas (US and India)

NOTE: Additional Holidays and vacations Durring Christmas and New Year is not counted in yet, I will update MB Sprint -4 and MB Sprint 5 Plans accordingly after confirmations on dates with Dev team and PMO.

Cool-off Periods/Buffers:

A cool-off period of 3 days has been included after every two sprint cycles. 

This is reflected in the gap between Sprint 2 and Sprint 3, which allows the team to recharge and conduct any necessary planning or retrospective activities.

NOTE : **We Need to incorporate teams PTOs as soon as available to manage bandwidth for each sprint durring Sprint planning sessions.

Smart Button


Emoji :link: Project information




Emoji :clipboard: Roadmap overview


Roadmap Planner


Emoji :mag: Detailed quarterly roadmap


Q1

Feature

Initiative

Dates

Priority

Effort

Status

Notes




High /Medium /Low

High /Medium /Low

In progress /not started /Shipped










Q2

Feature

Initiative

Dates

Priority

Effort

Status

Notes















Q3

Feature

Initiative

Dates

Priority

Effort

Status

Notes















Q4

Feature

Initiative

Dates

Priority

Effort

Status

Notes